Project Information
Clients:
KAO
Contract Value:
1.6 Million
Duration:
8 Months
Project Location:
Bishop Stortford
Scope of works

Molton Brown Bishop Stortford

JAG were engaged on this project for the full M&E works on a regeneration of mixing plant for Molton Brown cosmetic goods.

The mechanical works involved a new supply and extract ductwork system controlled via BMS. The pipework carrying products between tanks was stainless steel hygienic grade welded pipework. Other lines included; Hot and cold water, chilled water, compressed air, steam and waste water pipework.

The electrical works consisted of new distribution boards install, lighting, small power and a PLC control system to feed in